Matla Unit 1 ESP Refurbishment

The project scope entails the Refurbishment of Unit 4 Electrostatic Precipitator on a 24/7 shutdown basis. The scope included platework repairs to the 48 hoppers below the ESP and the ESP ducting, replacing and repairing various internal mechanical equipment, erection of new access platforms around the roof structure and internal to the ESP. The removal and reinstatement of fly-ash ducting, installation of new electrodes and collector plates, erection of new hot and cold roof structures and installation of new transformers and mechanicals on top of roof.

Client:

Lesedi Nuclear

Contract Duration: 6 months (2024)
Location:

Matla Power Station (Kriel)

Commodity: Ash
Value: R124m incl. extras