Medupi PJFF Maintenance Project 

The project entailed the 24 hours a day seven day a week maintenance, cleaning and sustaining full availability of the fine ash handling system of Medupi Power Station for generation units 3 and 2.

Client: Eskom – Medupi Power Station
Contract Duration: 12 Months (2019/2020)
Location: Lephalale, Limpopo
Commodity: Power Generation (Coal Fired)
Project Value: R36.7m