The project entailed the 24 hours a day seven day a week maintenance, cleaning and sustaining full availability of the fine ash handling system of Medupi Power Station for generation units 3 and 2.
Client: | Eskom – Medupi Power Station |
Contract Duration: | 12 Months (2019/2020) |
Location: | Lephalale, Limpopo |
Commodity: | Power Generation (Coal Fired) |
Project Value: | R36.7m |