Two Rivers Thickener Erection
The project scope entails the SMPP erection of three thickeners consisting of 1 x 10m dia storage tank, 1 x 15m dia HRT thickener and 1 x 50m dia cable torque thickener including access & maintenance platforms, thickener internals (rake, shaft), all mechanicals (drive, hydraulic power pack & piping), the cold commissioning of the thickeners up to C2 (water fill & leak detection.
Client: | FLSmidth |
Contract Duration: | 7 months |
Location: | Steelpoort |
Commodity: | Platinum |
Value: |
R7,538m |