Two Rivers Thickener Erection

The project scope entails the SMPP erection of three thickeners consisting of 1 x 10m dia storage tank, 1 x 15m dia HRT thickener and 1 x 50m dia cable torque thickener including access & maintenance platforms, thickener internals (rake, shaft), all mechanicals (drive, hydraulic power pack & piping), the cold commissioning of the thickeners up to C2 (water fill & leak detection.

Client: FLSmidth
Contract Duration: 7 months
Location: Steelpoort
Commodity: Platinum
Value:

R7,538m